Pages

Tuesday 17 February 2015

Fishing vessel transformed into a wave power plant



Date:               February 17, 2015
Source:           SINTEF
Summary:
Researchers are demonstrating that it is possible for a redundant fishing vessel to be used as a power plant. The first vessel of its kind is now anchored offshore in the Stadthavet area west in Norway, with the aim of generating electricity from the natural forces of the sea.


                             Is it possible for a redundant fishing vessel to be used as a power plant? Absolutely! The first vessel of its kind is now anchored offshore in the Stadthavet area west in Norway, with the aim of generating electricity from the natural forces of the sea.
                             The idea is as brilliant as it is simple.
"In principle, it works almost like a bicycle pump" says engineer and Project Manager Edgar Kvernevik at Kvernevik Engineering AS.
For the last two years his company has been working with Geir Arne Solheim, the founder of Havkraft AS and the man who came up with the idea, to develop and build the wave power plant now installed in a former trawler/autoline vessel.
But how do you get a fishing vessel to work like a gigantic bicycle pump?
The makers have met this challenge by installing four large chambers in the vessel's bow. As the waves strike the vessel, the water level in the chambers rises. This creates an increase in air pressure which in turn drives four turbines -- one for each chamber. The pitch of the vessel also contributes by generating additional air pressure in the chambers when the wave height is large. The design of the chambers is such that they work in response to different wave heights, which means that the energy is exploited very effectively.
"The plant thus produces electricity with the help of what is called a fluctuating water column," explains Kvernevik, who has spent much of his working life designing and building vessels. "All we have to do is to let the vessel swing at anchor in a part of the ocean with sufficient wave energy. Everything is designed to be remotely-controlled from onshore," he says.
New application of a tried and trusted principle
The company Havkraft AS, which came up with the original concept, is based in Raudeberg in Nordfjord. Solheim, the company's founder, has been working here with wave energy for more than 15 years. The company is now receiving funding from Innovation Norway to help put the idea into practice.
The "fluctuating water column" concept is a tried and trusted approach. However, installing a wave energy plant inside a fishing vessel is something no-one has done before.
"This floating power plant has also been equipped with a special anchoring system which means that it is always facing into the incoming waves," explains Kvernevik. "This ensures that the plant is in the optimal position at all times," he says.
Full overview of energy production
But Havkraft AS is not alone. One of the organisations contributing to the project is MARINTEK, which has developed a mathematical model and run a number of simulations of the plant. This has provided developers with a better overall picture of how much energy can be extracted from the waves. The project has advanced on the basis of analyses, model experiments and full-scale simulations.
"The use of simulations and dynamic analyses, in combination with model experiments, has enabled us to avoid beating repeatedly around the bush using the standard approach of trying out different scales of model," says Kvernevik. "This has saved us time and money. We now have a full-scale model constructed and installed," he says.
The nominal capacity of the plant is 4 x 50kW -- 200kW in total. MARINTEK's computations indicate that the plant is capable of producing 320,000 kWh per year.
Advanced engineering
Even though the principle behind the plant is simple, there is a lot of advanced engineering installed on board.
None of the moving parts are in direct contact with salt water. In fact, the only moving parts are the turbines, which are installed above the vessel's deck. Moreover, it is constructed so that it runs the same way regardless of whether the chambers are "inhaling" or "exhaling." The vessel is currently located offshore Stadtlandet, in an area where the company Stadt Wind AS has a renewable energy testing licence. This is one of three test sites in the Stadthavet area, which together comprise the so-called Stadt Test Area.
A study of an offshore wind farm (the 1080MW Stadtwind project, involving floating wind turbines) was previously carried out in the same area. The Norwegian Water Resources and Energy Directorate (NVE) subsequently declared the area as one of the few in Norway suitable for the installation of floating offshore wind farms. The annual average wind speed measured in the area is 11 m/s, which is higher than any other location in Norway, including the North Sea. This indicates that the area is clearly well suited to the exploitation of renewable energy from wind and waves, which is interesting because in the long-term, the project plans to look into the possibility of combining floating wave power plants with wind turbines.
Hydrogen production
"We see this project as a three-stage rocket," says Kvernevik.
"The first stage is to test the model we have just built to make sure that electricity generation can be carried out as planned. Next, a hydrogen production plant will be installed on board the vessel so that the electricity generated can be stored in the form of hydrogen gas. We have high hopes that hydrogen will be the car fuel of the future. Our aim is to work with others to produce hydrogen at a competitive price -- based on an infinite resource and involving no harmful emissions," says Kvernevik optimistically.
"The plan is then to construct a plant with a nominal capacity of 1000kW (1MW). We will do this by installing five production modules similar to the current plant either on a larger vessel or a custom-built barge. Finally, we will build a semi-submersible platform designed to carry a 4MW wave power plant with a 6MW wind turbine installed on top," he says.
MARINTEK in Trondheim is one of the project partners which have contributed towards the development of the wave power plant.
"We have built a basic computational model of the plant," says MARINTEK's Jørgen Hals Todalshaug, a hydrodynamicist and an expert in wave energy. The project will now be running a series of field tests at sea which will provide Havkraft AS with experience of how the plant works under operational conditions.
The tests will also provide quantitative data that can be used to improve and calibrate the computational model, and thus improve its accuracy.


Story Source:
The above story is based on materials provided by SINTEF. The original article was written by Christina Benjaminsen. Note: Materials may be edited for content and length.


Cite This Page:
SINTEF. "Fishing vessel transformed into a wave power plant." ScienceDaily. ScienceDaily, 9 February 2015. <www.sciencedaily.com/releases/2015/02/150209094940.htm>.

FROM,….
SCIENCEDAILY.COM

Saturday 10 January 2015

Computer Network PPT's (Part-1)- Download Here

Hi VIP's!
Computer network PPT's has been taken from Ravi shankar sir.
There are two PPT's available now. We add more in future.



This PPT consisting of two chapters. That is,
  • Chapter-5 (Congestion Control & Resource Allocation)
  • Chapter-6 (TCP & UDP Control Protocols)

http://www20.zippyshare.com/v/41153989/file.html

Tuesday 30 December 2014

Aptitude Questions- Part1

Hai Power Guys!
We are receiving Aptitude Questions Collections from Placement training persons.

We are knowing very well Aptitude is must for placement so kindly practice yourself with this Aptitude collections. We are upload more aptitude questions in future.
 Download Aptitude collections click the following link

https://www.dropbox.com/s/m5ppe8g7inoj6zn/Aptitude_Collections_1.zip?dl=0



Saturday 27 December 2014

Intimation About Placement Training

This is to that all students are asked to bring the amount for workshop worth 1000/- on Monday .

The amount must be paid whether you attend or not. So the students are adviced to attend the Workshop. And handover the money to our Class Representative.
By
 Our Class Advisor.

MP&MC Lab Manual

This is an complete manual of Microprocessor and Microcontroller Lab....By Clicking on to this link you will a open a Word document file download from the link......

By clicking this you can download the document

https://www.dropbox.com/s/e4txk58txy5n0r4/MICROPROCESSOR%20MANUAL.doc?dl=0

New Intimation to our students

Hi Frnz ...... This Blogspot is used to intimate the informations given by our class advisor and also is used share the manuals and few more informations....Use it regularly and keep updated with us